New plan will increase recovery from Gullfaks

15/01/2019 A new, amended Plan for development and operation (PDO) describes the next phase in production from limestone rocks over the Gullfaks field in the North Sea. The increased reserves are estimated at 2.8 million standard cubic metres (nearly 18 million bbls) of oil equivalents.

The Norwegian Petroleum Directorate (NPD) recently received the plan from the operator, Equinor. According to the plan, NOK 2.23 billion will be invested to recover more of the reserves in the tight zones in the Shetland Group and the Lista Formation.

These reservoirs are located over the Gullfaks field, 1700-2000 metres below the seabed, and they have been producing since 2013. Now the plan is to increase production by injecting water for pressure support.

The plan also describes further recovery from the underlying main reservoirs on Gullfaks.

“A further development of Shetland/Lista with water injection is a good contribution to increased oil recovery on Gullfaks,” says Arvid Østhus (picture), the NPD’s assistant director for development and operations in the northern North Sea.

“The project is also a positive example that, in some cases, tight reservoirs can be developed profitably through good studies and new technology. The NPD has conducted a mapping study which shows that there are significant resources present in tight reservoirs on the Norwegian Shelf. The Shetland/Lista project shows that it is possible to extract such resources.”

The plan includes a change in the drainage strategy for the reservoir in Shetland/Lista, from depressurisation to water injection, through drilling horizontal wells from the Gullfaks facilities.

Up to 2013, the understanding was that the resources in the tight limestone reservoir in Shetland/Lista over Gullfaks could not be recovered. However, new information showed that the oil can still be produced through natural fractures in the reservoir.

In 2015, the authorities approved an amended PDO for development of this deposit. Recovery of the resources was to take place through production from existing wells down to a defined reservoir pressure. Pilot tests were also to be conducted by injecting water to test the potential for improved recovery. This water injection yielded positive results. That, along with extensive reservoir studies, formed the basis for a new, amended PDO with water injection as drainage strategy.

The licensees in the production licence are Equinor (operator, 51 per cent), Petoro (30 per cent) and OMV (19 per cent).

Read more about Gullfaks: https://www.norskpetroleum.no/en/facts/field/gullfaks/

 

Gullfaks A-innretningen (Foto: Equinor)

Gullfaks A
(Photo: Equinor)

Updated: 25/02/2019

Latest news

Dry well in the Norwegian Sea (6507/2-8)
27/03/2025 Aker BP ASA and its partners have completed drilling on the “Kongeørn” prospect in the Norwegian Sea, 240 kilometres west of Sandnessjøen.
Drilling permit for wellbore 25/11-30 S
27/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 25/11-30 S in production licence 169, cf. Section 13 of the Resource Management Regulations.
Dry well in the North Sea (35/6-6)
26/03/2025 OMV and its partners have drilled a dry well on the “Horatio” prospect in the North Sea.
Production figures Febuary 2025
20/03/2025 Preliminary production figures for February 2025 show an average daily production of 1 938 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 9/6-1
18/03/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 9/6-1 in production licence EXL006, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6405/7-4
17/03/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6405/7-4 in production licence 1005, cf. Section 13 of the Resource Management Regulations.
Drilling permit for the wells 34/6-8 S and 34/6-8 A
11/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for the wells 34/6-8 S and 34/6-8 A in production licence 554, cf. Section 13 of the Resource Management Regulations.
Announcement of acreage for CO2 storage on the Norwegian Continental Shelf
05/03/2025 On 5th of March 2025, the Ministry of Energy announced one area for CO2 storage pursuant to the CO2 Storage Regulations. This area comprises defined blocks in the North Sea.
Gas/condensate discovery in the Norwegian Sea (6406/6-7 S)
05/03/2025 Equinor and its partners have proven gas/condensate in the “Mistral Sør” prospect.
Dry well in the North Sea (7/1-4 S)
04/03/2025 Vår Energi and its partners have drilled a dry well on the “Kokopelli” prospect, south of the Sleipner area.