Plans to re-develop Tor
01/07/2019
On behalf of the licensees, operator Conoco Phillips has submitted a Plan for Development and Operation (PDO) for a re-development of the Tor field in the Greater Ekofisk area in the North Sea.
The field was in production from 1978 until it was shut down in 2015 when the installation reached the end of its lifetime. At shutdown, just 20 per cent of the resources in place had been produced.
The field will be re-developed by installing two new subsea templates tied into the Ekofisk Complex. The recoverable reserves are estimated at 10 million standard cubic metres of oil equivalents (Sm3).
The plan is to re-start production in late 2020. The total investment costs for the re-development are estimated at six billion kroner.
Updated: 01/07/2019
Latest news
Drilling permit for wellbore 25/11-30 S
27/03/2025
The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 25/11-30 S in production licence 169, cf. Section 13 of the Resource Management Regulations.
Production figures Febuary 2025
20/03/2025
Preliminary production figures for February 2025 show an average daily production of 1 938 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 9/6-1
18/03/2025
The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 9/6-1 in production licence EXL006, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6405/7-4
17/03/2025
The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6405/7-4 in production licence 1005, cf. Section 13 of the Resource Management Regulations.
Drilling permit for the wells 34/6-8 S and 34/6-8 A
11/03/2025
The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for the wells 34/6-8 S and 34/6-8 A in production licence 554, cf. Section 13 of the Resource Management Regulations.