Start-up consent for Tor II

Tor-II-saken.png

30/09/2020 The licensees in the Tor Unit in the southern North Sea have secured consent to start up the Tor II facilities.

The Tor field was proven in 1970 and was in production from 1978 to 2015, when it was shut down.

In the summer of 2019, the licensees submitted a plan for development and operation (PDO) for a new development of the field, called Tor II. The plan was approved by the Ministry of Petroleum and Energy in the autumn of 2019.

The Norwegian Petroleum Directorate has now granted consent for start-up of the Tor II facilities from 1 November 2020.

“Tor is the first field on the Norwegian shelf with a complete redevelopment, receiving consent to start up after having been shut down. We are satisfied that the licensees have found solutions for even better utilisation of the resources in the Tor field,” says Arvid Østhus, the NPD’s assistant director of development and operations – North Sea.

Tor II comprises two new subsea templates to be installed on the Tor field and tied in to Ekofisk, about 13 kilometres away. Eight new production wells will be drilled. The recoverable reserves were estimated at 10 million standard cubic metres of oil equivalent (Sm3) in the PDO.

Operator ConocoPhillips plans start-up in the fourth quarter of 2020, in line with the description in the PDO.

“Tor II shows that shut down fields can create significant values if they are redeveloped. We have produced oil and gas on the NCS for nearly 50 years, and the industry has undergone enormous development through this period. That’s why it’s so great that fields once shut down because they were not profitable can become profitable again today,” says Østhus.

 

Contact
postboks@sodir.no

Tel: +47 51 87 60 00

Updated: 10/02/2025

Latest news

Dry well in the Norwegian Sea (6507/2-8)
27/03/2025 Aker BP ASA and its partners have completed drilling on the “Kongeørn” prospect in the Norwegian Sea, 240 kilometres west of Sandnessjøen.
Drilling permit for wellbore 25/11-30 S
27/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 25/11-30 S in production licence 169, cf. Section 13 of the Resource Management Regulations.
Dry well in the North Sea (35/6-6)
26/03/2025 OMV and its partners have drilled a dry well on the “Horatio” prospect in the North Sea.
Production figures Febuary 2025
20/03/2025 Preliminary production figures for February 2025 show an average daily production of 1 938 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 9/6-1
18/03/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 9/6-1 in production licence EXL006, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6405/7-4
17/03/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6405/7-4 in production licence 1005, cf. Section 13 of the Resource Management Regulations.
Drilling permit for the wells 34/6-8 S and 34/6-8 A
11/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for the wells 34/6-8 S and 34/6-8 A in production licence 554, cf. Section 13 of the Resource Management Regulations.
Announcement of acreage for CO2 storage on the Norwegian Continental Shelf
05/03/2025 On 5th of March 2025, the Ministry of Energy announced one area for CO2 storage pursuant to the CO2 Storage Regulations. This area comprises defined blocks in the North Sea.
Gas/condensate discovery in the Norwegian Sea (6406/6-7 S)
05/03/2025 Equinor and its partners have proven gas/condensate in the “Mistral Sør” prospect.
Dry well in the North Sea (7/1-4 S)
04/03/2025 Vår Energi and its partners have drilled a dry well on the “Kokopelli” prospect, south of the Sleipner area.