30/09/2020 The licensees in the Tor Unit in the southern North Sea have secured consent to start up the Tor II facilities.

The Tor field was proven in 1970 and was in production from 1978 to 2015, when it was shut down.

In the summer of 2019, the licensees submitted a plan for development and operation (PDO) for a new development of the field, called Tor II. The plan was approved by the Ministry of Petroleum and Energy in the autumn of 2019.

The Norwegian Petroleum Directorate has now granted consent for start-up of the Tor II facilities from 1 November 2020.

“Tor is the first field on the Norwegian shelf with a complete redevelopment, receiving consent to start up after having been shut down. We are satisfied that the licensees have found solutions for even better utilisation of the resources in the Tor field,” says Arvid Østhus, the NPD’s assistant director of development and operations – North Sea.

Tor II comprises two new subsea templates to be installed on the Tor field and tied in to Ekofisk, about 13 kilometres away. Eight new production wells will be drilled. The recoverable reserves were estimated at 10 million standard cubic metres of oil equivalent (Sm3) in the PDO.

Operator ConocoPhillips plans start-up in the fourth quarter of 2020, in line with the description in the PDO.

“Tor II shows that shut down fields can create significant values if they are redeveloped. We have produced oil and gas on the NCS for nearly 50 years, and the industry has undergone enormous development through this period. That’s why it’s so great that fields once shut down because they were not profitable can become profitable again today,” says Østhus.

 

Contact
Eldbjørg Vaage Melberg

Tel: +47 51 87 61 00

Updated: 30/09/2020

Latest news

Production figures October 2024
20/11/2024 Preliminary production figures for October 2024 show an average daily production of 1 988 000 barrels of oil, NGL and condensate.
Oil and gas discovery in the North Sea (35/11-30 S and 35/11-30 A)
14/11/2024 Equinor and its partners have made an oil and gas discovery in wildcat wells 35/11-30 S and 35/11-30 A (“Rhombi”) in the North Sea.
Stay up to date with news from the Directorate
12/11/2024 Did you know that you can receive alerts about our news items straight to your inbox?
Drilling permit for wellbore 6305/10-1
11/11/2024 The Norwegian Offshore Directorate has granted Orlen Upstream Norway AS drilling permit for wellbore 6305/10-1 in production licence 1055, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 7122/9-2
04/11/2024 The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 7122/9-2 in production licence 1131, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 31/4-A-23 F
24/10/2024 The Norwegian Offshore Directorate has granted OKEA ASA drilling permit for wellbore 31/4-A-23 F in production licence 055, cf. Section 13 of the Resource Management Regulations.
Production figures September 2024
21/10/2024 Preliminary production figures for September 2024 show an average daily production of 1 720 000 barrels of oil, NGL and condensate.
Revised dataset that could facilitate CO2 storage planning
16/10/2024 The Norwegian Offshore Directorate has reviewed around 800 wells and revised the top and bottom for the Utsira Group and the Skade Formation, to ensure consistency.
Drilling permit for the wells 7122/7-8 and 7122/8-3 S
10/10/2024 The Norwegian Offshore Directorate has granted Vår energi ASA drilling permit for the wells 7122/7-8 and 7122/8-3 S in production licence 229, cf. Section 13 of the Resource Management Regulations.
Delineation of discovery in the Norwegian Sea (6507/2-7 S)
03/10/2024 Aker BP has proven gas in appraisal well 6507/2-7 S in the Norwegian Sea, 230 kilometres west of Sandnessjøen.