26/06/2020 The companies are considering multiple electrification projects that could reduce emissions considerably.

Today, eight fields on the Norwegian shelf receive power from the Norwegian power grid. Decisions have also been made to supply another eight fields with power in this manner. This means that total CO2 emissions will be about 3.2 million tonnes lower per year than they otherwise would have been.

An additional six electrification projects are approaching an investment decision. If they are adopted, the avoided emissions will amount to approx. 4.9 million tonnes of CO2 per year. The Norwegian Petroleum Directorate's projections show that, at this point, more than 50 per cent of Norwegian petroleum production will be run on power from shore in the mid-2020s.

This emerges in a report the Norwegian Petroleum Directorate has prepared in collaboration with the Norwegian Water Resources and Energy Directorate (NVE), the Norwegian Environment Agency and the Petroleum Safety Authority. The report was submitted to Minister of Petroleum and Energy Tina Bru on Friday, 26 June.

"In a few years, power from shore can allow us to avoid CO2 emissions equivalent to ten per cent of total Norwegian greenhouse gas emissions. At this point, almost half of Norway’s oil and gas production will be running on power from shore", says Director General Ingrid Sølvberg.

"The companies are also working on several projects that could provide additional emission cuts beyond this".

Electrified fields and adopted projects

Today, the Troll, Gjøa, Ormen Lange, Valhall, Goliat and Johan Sverdrup fields have facilities supplied with power directly from shore. Vega is also operated with power from shore via its host installation Gjøa, and Hod via Valhall.

The Martin Linge field, which is under development, will be supplied with power directly from shore. The Edvard Grieg, Ivar Aasen, Gina Krog, Solveig and Hanz fields will receive power from the area solution on the Utsira High, which is part of the Johan Sverdrup field's second phase. The Duva and Nova fields will be operated with power from shore via Gjøa.

Power from shore to these 16 fields will lead to a reduction in CO2 emissions in Norway of 3.2 million tonnes per year, compared to what they would otherwise have been.

Power from shore in the planning phase

In addition to the 16 fields that are either operated with power from shore or where this has been adopted, six other projects have reached an advanced stage of the planning phase. These projects are on Troll B, Troll C, Oseberg Field Centre and Oseberg Sør, Sleipner and the Melkøya onshore facility.

An investment decision was made for Sleipner in May and the project is now under regulatory review. The project will also provide power from shore to the associated fields Gudrun, Sigyn, Gugne and Utgard.

The companies have reported data about the projects in the planning phase based on their studies. The report features calculated measure costs based on these data. The calculations show that the projects have a measure cost of below NOK 1500 per tonne of CO2.

The projects representing the greatest emission reductions are the Melkøya onshore facility, Troll B, Troll C, Oseberg Field Centre and Oseberg Sør.

The companies have reported that all the planned projects could be in operation from the mid-2020s.

Onshore power system

"Electrification of the shelf will have consequences for the power system both in the form of somewhat higher electricity prices and a need for increased investments onshore", says NVE Director General Kjetil Lund.

The six projects in advanced stages of the planning phase will increase annual power consumption in Norway by up to 4 TWh, or about 3 per cent per year.

The power from shore projects will lead to an increase in electricity prices in Norway, and smaller differences in electricity prices between the north and south in Norway. One important precondition is that the onshore power system can handle the increase in consumption, without this negatively affecting security of supply for existing customers.

Most power from shore projects that are under planning will require measures in the power grid. Electrification of the onshore facility on Melkøya requires the construction of a new power line.

It is also the case that, with the currently planned grid investments, the onshore facility on Melkøya, Troll B and C, Oseberg Field Centre and Oseberg Sør will have to be disconnected in strained situations in the power grid, and potentially use their own back-up power supply.

Update

The report is an update of the Power from shore report presented in 2008. Subsequent technology development has made power from shore projects more cost-effective. This is because it is now possible to transmit alternating current over greater distances, and thus reach more facilities.

A solution with alternating current does not require as much equipment on the platforms as direct current. Technology has also been developed for power from shore to floating production vessels (FPSOs).

 

Read more

Summary of the report "Power from shore to the Norwegian shelf", 2020 (in English)

The report "Power from shore to the Norwegian shelf", 2020 (in Norwegian)

 

Ingrid-Solvberg-OED-Kraft-fra-land-rapport-2020.jpg

The report is handed over to the Minister of Petroleum and Energy, Tina Bru. From left: Anne Vera Skrivarhaug (NVE), Tina Bru and Director general Ingrid Sølvberg.

Updated: 26/06/2020

Latest news

Dry well in the Norwegian Sea (6305/10-1)
22/01/2025 Orlen Upstream Norway and its partner Norske Shell have drilled a dry well, wildcat well 6305/10-1 “Tomcat”, in the southern part of the Norwegian Sea.
Production figures December 2024
21/01/2025 Preliminary production figures for December 2024 show an average daily production of 2 017 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 35/6-6
21/01/2025 The Norwegian Offshore Directorate has granted OMV (Norge) AS drilling permit for wellbore 35/6-6 in production licence 1109, cf. Section 13 of the Resource Management Regulations.
Gas discovery in the Barents Sea (7122/9-2)
17/01/2025 Vår Energi ASA and its partners found gas in the “Elgol” prospect; however, preliminary estimates indicate that the discovery is not profitable given current price assumptions.
20 companies offered ownership interests
14/01/2025 In the 2024 awards in pre-defined areas (APA), 20 companies have been offered ownership interests in a total of 53 production licences on the Norwegian continental shelf (NCS).
Dry well in the North Sea (24/12-8 S)
14/01/2025 Aker BP and its partner Concedo drilled the dry well 24/12-8 S near the Bøyla field in the North Sea.
Record-high gas production in 2024
09/01/2025 The Norwegian Offshore Directorate's summary of activity on the Norwegian continental shelf in 2024 shows that gas production is higher than ever.
Drilling permit for wellbore 35/10-15 S
08/01/2025 The Norwegian Offshore Directorate has granted DNO Norge AS drilling permit for wellbore 35/10-15 S in production licence 1182 S, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6507/2-8
08/01/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6507/2-8 in production licence 942, cf. Section 13 of the Resource Management Regulations.
Dry wells in the North Sea (35/10-14 S and A)
23/12/2024 Equinor and its partners have drilled two dry wells (“Kvernbit/Mimung”) in the North Sea.