26/06/2020 The companies are considering multiple electrification projects that could reduce emissions considerably.

Today, eight fields on the Norwegian shelf receive power from the Norwegian power grid. Decisions have also been made to supply another eight fields with power in this manner. This means that total CO2 emissions will be about 3.2 million tonnes lower per year than they otherwise would have been.

An additional six electrification projects are approaching an investment decision. If they are adopted, the avoided emissions will amount to approx. 4.9 million tonnes of CO2 per year. The Norwegian Petroleum Directorate's projections show that, at this point, more than 50 per cent of Norwegian petroleum production will be run on power from shore in the mid-2020s.

This emerges in a report the Norwegian Petroleum Directorate has prepared in collaboration with the Norwegian Water Resources and Energy Directorate (NVE), the Norwegian Environment Agency and the Petroleum Safety Authority. The report was submitted to Minister of Petroleum and Energy Tina Bru on Friday, 26 June.

"In a few years, power from shore can allow us to avoid CO2 emissions equivalent to ten per cent of total Norwegian greenhouse gas emissions. At this point, almost half of Norway’s oil and gas production will be running on power from shore", says Director General Ingrid Sølvberg.

"The companies are also working on several projects that could provide additional emission cuts beyond this".

Electrified fields and adopted projects

Today, the Troll, Gjøa, Ormen Lange, Valhall, Goliat and Johan Sverdrup fields have facilities supplied with power directly from shore. Vega is also operated with power from shore via its host installation Gjøa, and Hod via Valhall.

The Martin Linge field, which is under development, will be supplied with power directly from shore. The Edvard Grieg, Ivar Aasen, Gina Krog, Solveig and Hanz fields will receive power from the area solution on the Utsira High, which is part of the Johan Sverdrup field's second phase. The Duva and Nova fields will be operated with power from shore via Gjøa.

Power from shore to these 16 fields will lead to a reduction in CO2 emissions in Norway of 3.2 million tonnes per year, compared to what they would otherwise have been.

Power from shore in the planning phase

In addition to the 16 fields that are either operated with power from shore or where this has been adopted, six other projects have reached an advanced stage of the planning phase. These projects are on Troll B, Troll C, Oseberg Field Centre and Oseberg Sør, Sleipner and the Melkøya onshore facility.

An investment decision was made for Sleipner in May and the project is now under regulatory review. The project will also provide power from shore to the associated fields Gudrun, Sigyn, Gugne and Utgard.

The companies have reported data about the projects in the planning phase based on their studies. The report features calculated measure costs based on these data. The calculations show that the projects have a measure cost of below NOK 1500 per tonne of CO2.

The projects representing the greatest emission reductions are the Melkøya onshore facility, Troll B, Troll C, Oseberg Field Centre and Oseberg Sør.

The companies have reported that all the planned projects could be in operation from the mid-2020s.

Onshore power system

"Electrification of the shelf will have consequences for the power system both in the form of somewhat higher electricity prices and a need for increased investments onshore", says NVE Director General Kjetil Lund.

The six projects in advanced stages of the planning phase will increase annual power consumption in Norway by up to 4 TWh, or about 3 per cent per year.

The power from shore projects will lead to an increase in electricity prices in Norway, and smaller differences in electricity prices between the north and south in Norway. One important precondition is that the onshore power system can handle the increase in consumption, without this negatively affecting security of supply for existing customers.

Most power from shore projects that are under planning will require measures in the power grid. Electrification of the onshore facility on Melkøya requires the construction of a new power line.

It is also the case that, with the currently planned grid investments, the onshore facility on Melkøya, Troll B and C, Oseberg Field Centre and Oseberg Sør will have to be disconnected in strained situations in the power grid, and potentially use their own back-up power supply.

Update

The report is an update of the Power from shore report presented in 2008. Subsequent technology development has made power from shore projects more cost-effective. This is because it is now possible to transmit alternating current over greater distances, and thus reach more facilities.

A solution with alternating current does not require as much equipment on the platforms as direct current. Technology has also been developed for power from shore to floating production vessels (FPSOs).

 

Read more

Summary of the report "Power from shore to the Norwegian shelf", 2020 (in English)

The report "Power from shore to the Norwegian shelf", 2020 (in Norwegian)

 

Ingrid-Solvberg-OED-Kraft-fra-land-rapport-2020.jpg

The report is handed over to the Minister of Petroleum and Energy, Tina Bru. From left: Anne Vera Skrivarhaug (NVE), Tina Bru and Director general Ingrid Sølvberg.

Updated: 26/06/2020

Latest news

Announcement of awards in predefined areas (APA) 2024
08/05/2024 The Ministry of Energy announced APA 2024 on 8 May 2024, encompassing the predefined areas with blocks in the Norwegian Sea, Norwegian Sea and Barents Sea.
Drilling permission for the wells 7324/6-2 and 7324/8-4
06/05/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for the wells 7324/6-2 and 7324/8-4 in production license 1170, cf. Section 13 of the Resource Management Regulations.
Eight companies have applied for CO2 storage acreage
30/04/2024 The Norwegian Ministry of Energy has received applications from eight companies in connection with the announcement of two areas in the North Sea for potential storage of CO2 on the Norwegian shelf.
Invitation to nominate blocks for mineral activities on the seabed
29/04/2024 In a letter of 29 April, the Norwegian Offshore Directorate invited players to nominate blocks in connection with the first licensing round for mineral activities on the seabed.
Drilling permission for wells 35/10-14 S and 35/10-14 A
29/04/2024 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wells 35/10-14 S and 35/10-14 A in production license 1185, cf. Section 13 of the Resource Management Regulations.
Well for data acquisition on Wisting
22/04/2024 Equinor has completed an appraisal well (7324/7-4) on the Wisting discovery in the Barents Sea. The objective was to acquire data on the reservoir and cap rock, for use in ongoing evaluation and development of the discovery.
Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.