Dvalin ready for start-up

Wintershall-DEA-Dvalin-structure-illustration

The gas and condensate from Dvalin will be sent to the Heidrun field for further processing and export. (illustration: Wintershall DEA)

21/10/2020 The authorities have issued consent for start-up of the Dvalin field in the Norwegian Sea. Operator Wintershall Dea estimates that it can recover 18 billion standard cubic metres of gas from Dvalin.

The operator's investment projection for the development is approx. NOK 11 billion. Wintershall Dea expects to start up in November/December.

The field is located in production license PL435. It consists of two structures situated 3.5 kilometres apart. Dvalin øst was proven in 2010 and Dvalin vest in 2012.

The wellstream from Dvalin will be sent to the Heidrun field, which is located south-east of Dvalin, for further processing and export. The gas will be exported via the Polarled pipeline into Nyhamna in Central Norway. The condensate will be routed to the existing process plant on Heidrun and onward via the Heidrun storage ship to tankers for further transport to an oil refinery.

"The development of Dvalin is a textbook example of good utilisation of existing infrastructure in the area", says Tove Francke, Assistant Director for Development and Operations in the Norwegian Petroleum Directorate.

Dvalin was planned as a development with four vertical production wells, two for the eastern part and two for the western part of the field. Drilling and completion of the four production wells started in August 2019 and is now complete.

Updated: 22/10/2020

Latest news

Announcement of awards in predefined areas (APA) 2024
08/05/2024 The Ministry of Energy announced APA 2024 on 8 May 2024, encompassing the predefined areas with blocks in the Norwegian Sea, Norwegian Sea and Barents Sea.
Drilling permission for the wells 7324/6-2 and 7324/8-4
06/05/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for the wells 7324/6-2 and 7324/8-4 in production license 1170, cf. Section 13 of the Resource Management Regulations.
Eight companies have applied for CO2 storage acreage
30/04/2024 The Norwegian Ministry of Energy has received applications from eight companies in connection with the announcement of two areas in the North Sea for potential storage of CO2 on the Norwegian shelf.
Invitation to nominate blocks for mineral activities on the seabed
29/04/2024 In a letter of 29 April, the Norwegian Offshore Directorate invited players to nominate blocks in connection with the first licensing round for mineral activities on the seabed.
Drilling permission for wells 35/10-14 S and 35/10-14 A
29/04/2024 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wells 35/10-14 S and 35/10-14 A in production license 1185, cf. Section 13 of the Resource Management Regulations.
Well for data acquisition on Wisting
22/04/2024 Equinor has completed an appraisal well (7324/7-4) on the Wisting discovery in the Barents Sea. The objective was to acquire data on the reservoir and cap rock, for use in ongoing evaluation and development of the discovery.
Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.