Go-ahead for Gjøa expansion

18/12/2020 The authorities have granted consent for start-up of a subsea installation with two new wells on the Gjøa field in the North Sea.

Operator Neptune Energy estimates the project will add 2.4 million standard cubic metres of oil equivalent (15 million bbls o.e.) from Gjøa.

Gjøa is a gas and oil field located off the coast of Florø. The new wells are linked to the P1 segment, one of seven segments on the field.

Continued work on Gjøa resulted in the licensees submitting an application for exemption from a Plan for development and operation (PDO) for the P1 segment in February 2019. A four-slot well template has been put into place and two wells have been drilled.

According to the operator, the project has cost approx. NOK four billion. Neptune Energy expects start-up in January 2021.

PL 153 is the production licence.

“Further development of the P1 segment in Gjøa results in additional resources and increased values for Gjøa, and contributes to good utilisation of the production capacity and infrastructure in the area,” says Arvid Østhus, the NPD’s Assistant Director Development and Operations – North Sea.

Illustration showing the seabed installations on the Gjøa field
Further development of Gjøa yields additional resources of around 15 million barrels of oil equivalent. (illustration: Neptune Energy)

Updated: 18/12/2020

Latest news

Dry well in the Norwegian Sea (6507/2-8)
27/03/2025 Aker BP ASA and its partners have completed drilling on the “Kongeørn” prospect in the Norwegian Sea, 240 kilometres west of Sandnessjøen.
Drilling permit for wellbore 25/11-30 S
27/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 25/11-30 S in production licence 169, cf. Section 13 of the Resource Management Regulations.
Dry well in the North Sea (35/6-6)
26/03/2025 OMV and its partners have drilled a dry well on the “Horatio” prospect in the North Sea.
Production figures Febuary 2025
20/03/2025 Preliminary production figures for February 2025 show an average daily production of 1 938 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 9/6-1
18/03/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 9/6-1 in production licence EXL006, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6405/7-4
17/03/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6405/7-4 in production licence 1005, cf. Section 13 of the Resource Management Regulations.
Drilling permit for the wells 34/6-8 S and 34/6-8 A
11/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for the wells 34/6-8 S and 34/6-8 A in production licence 554, cf. Section 13 of the Resource Management Regulations.
Announcement of acreage for CO2 storage on the Norwegian Continental Shelf
05/03/2025 On 5th of March 2025, the Ministry of Energy announced one area for CO2 storage pursuant to the CO2 Storage Regulations. This area comprises defined blocks in the North Sea.
Gas/condensate discovery in the Norwegian Sea (6406/6-7 S)
05/03/2025 Equinor and its partners have proven gas/condensate in the “Mistral Sør” prospect.
Dry well in the North Sea (7/1-4 S)
04/03/2025 Vår Energi and its partners have drilled a dry well on the “Kokopelli” prospect, south of the Sleipner area.