14/11/2020
The expansion of the Snorre field in the North Sea consists of six subsea templates, which will be tied into Snorre A. Now the authorities have given Equinor and its partners consent to start up.
24 new wells, 13 production wells and 11 VAG (water-alternating gas) injectors will be drilled.
The recoverable reserves were calculated at approx. 31 million standard cubic metres of oil equivalent (195 million barrels) in the amended plan for development and operation (PDO). This corresponds to about twice the oil reserves in the Gina Krog field in the North Sea.
“The expansion of Snorre is a result of tireless work by both the companies and the authorities; work which has been ongoing for close to 15 years,” says Arvid Østhus, the NPD’s assistant director development and operations – North Sea.
The Snorre field was proven in 1979 and currently produces from the Snorre A, Snorre B and Snorre UPA facilities. In 2018, the licensees submitted an amended PDO for a redevelopment of the field, called the Snorre Expansion Project, and this was approved by the Ministry of Petroleum and Energy in the summer of 2018.
11/11/2024
The Norwegian Offshore Directorate has granted Orlen Upstream Norway AS drilling permit for wellbore 6305/10-1 in production licence 1055, cf. Section 13 of the Resource Management Regulations.
04/11/2024
The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 7122/9-2 in production licence 1131, cf. Section 13 of the Resource Management Regulations.
24/10/2024
The Norwegian Offshore Directorate has granted OKEA ASA drilling permit for wellbore 31/4-A-23 F in production licence 055, cf. Section 13 of the Resource Management Regulations.
16/10/2024
The Norwegian Offshore Directorate has reviewed around 800 wells and revised the top and bottom for the Utsira Group and the Skade Formation, to ensure consistency.