Planning redevelopment of the Hod field

Hod_B_final_large.jpg

Illustration of the Hod field, Aker BP.

24/06/2020 On behalf of the licensees, operator Aker BP has submitted a Plan for Development and Operation (PDO) for a redevelopment of the Hod field in the Valhall area in the North Sea.

The field was in production via a dedicated unstaffed wellhead platform, remote-controlled from Valhall, from 1990 until it was shut down in 2012. There has also been limited production from the Hod field via the Valhall Flank South platform.

When the Hod wellhead platform was shut down, just 20 per cent of the resources in place had been produced. The shutdown platform will be removed in accordance with a previously approved cessation plan.

The field will be redeveloped by installing a new wellhead platform tied in to the Valhall field centre. The recoverable reserves are estimated at about 6.4 MSm3 oil equivalents.

"Very gratifying"

The plan is to resume production at the beginning of 2022. The total investment costs for the redevelopment are estimated at NOK 5.7 billion.

“It is very gratifying that the companies have found it profitable to redevelop Hod to increase recovery of the remaining resources,” says Arvid Østhus, assistant director in Development and operations.

 

Contact
Eldbjørg Vaage Melberg

Tel: +47 51 87 61 00

Updated: 24/06/2020

Latest news

Production figures November 2024
20/12/2024 Preliminary production figures for November 2024 show an average daily production of 1 975 000 barrels of oil, NGL and condensate.
What would you like to learn more about at Technology Day 2025?
20/12/2024 The Norwegian Offshore Directorate is hosting a Technology Day on 5 June 2025 in Stavanger – and now you can nominate suggested lectures for the event.
Three companies offered acreage for CO2 storage
19/12/2024 Today, three companies have been offered exploration licences for CO2 storage in two areas in the North Sea.
The Shelf in 2024 will be presented on 9 January
19/12/2024 On 9 January 2025 at 10:00 o'clock, you can hear the figures, trends and stories straight from Director general Torgeir Stordal.
Drilling permit for the wells 6306/6-3 S and 6507/5-13 S
19/12/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6306/6-3 S in production licence 886 and 6507/5-13 S in production licence 212, cf. Section 13 of the Resource Management Regulations.
Oil and gas discovery in the North Sea (31/1-4)
17/12/2024 Equinor and its partners have discovered oil and gas in wildcat well 31/1-4 (“Ringand) in the North Sea.
Oil discovery near the Goliat field (7122/8-2 S)
16/12/2024 Vår Energi and its partner Equinor have proven oil in well 7122/8-2 S in the Barents Sea.
Dry well in the North Sea (34/6-7 S)
13/12/2024 Aker BP and its partners have drilled wildcat well 34/6-7 S (“Kaldafjell”) in the northern part of the North Sea.
Delimited discovery in the Norwegian Sea (6507/4-5 S)
10/12/2024 Wintershall Dea (Harbour Energy) has proven gas in appraisal well 6507/4-5 S in the Norwegian Sea, 270 kilometres north of Kristiansund.
Dry well in the Norwegian Sea (6608/10-R-2 H)
03/12/2024 The “Løvmeis” prospect in the Norwegian Sea, drilled by Equinor, has proven to be dry.