7/2/2021 Licensees in Troll Nord in the North Sea have secured consent to start up facilities and modifications associated with the Troll phase 3 project.

The PDO for Troll phase 3 was approved in December 2018. The project is a further development of the Troll field and will produce the gas from Troll Vest.

The development solution chosen by the operator Equinor and its partners comprises two subsea templates with eight gas wells tied into the Troll A platform. The wellstream from these wells is routed to Troll A through a new 36-inch pipeline, for further compression and export via existing infrastructure.

Recoverable reserves from Troll phase 3, mainly gas, are estimated at about 2.2 billion barrels (350 million standard cubic metres) of oil equivalent.

Major supplier of gas to the continent

"Troll is a giant on the Norwegian shelf. The field supplies as much as 7 per cent of Europe’s daily demand for gas, and Troll phase 3 will help maintain a high level of production for a long time to come," says Wenche Tjelta Johansen, Leader of Licence management.

The licensees have invested just over 8 billion kroner in Troll phase 3, and the plan is for it to produce for at least 30 years. Troll phase 3 was originally scheduled to come on stream this spring, but start-up was postponed until the autumn due to the Covid-19 restrictions.

Troll was proven in 1979, and the original plan for development and operation (PDO) was approved in 1986. The plan was updated in 1990 in order to move the gas processing to the Kollsnes terminal. The field came on stream in 1995.

Developed in phases

Troll was developed in phases, with gas extraction from Troll Øst in phase 1 and oil from Troll Vest in phase 2. Troll phase 1 was developed with Troll A, which is a fixed foundation wellhead and compression installation with a concrete substructure. Troll A receives power from shore. Gas compression capacity was expanded on Troll A in 2004/2005 and again in 2015.

Troll phase 2 was developed with Troll B, which is a floating living quarters and production facility in concrete, and Troll C, which is a semi-submersible living quarters and production facility in steel.

The oil in Troll Vest is produced from multiple subsea templates tied into Troll B and Troll C via pipelines. Production from the Troll C installation started in 1999. Troll C is also used for production from Fram, Fram H-Nord and Byrding. Several amended development plans (PDOs) were approved in connection with installing multiple subsea templates on Troll Vest.

Illustration showing Troll phase 3 expansion

Illustration of Troll phase 3: Equinor.

 

Contact

Ola Anders Skauby

Director Communication, public affairs and emergency response

Tel: +47 905 98 519

Updated: 7/2/2021

Latest news

Oil discovery in the North Sea (31/4-A-15 B)
9/11/2025 OKEA and its partners have made an oil discovery near the Brage field.
Drilling permit for wellbore 6507/8-12 S
9/11/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 6507/8-12 S in production licence 124 B.
Invitation to nominate blocks for the 26th licensing round
9/10/2025 The Norwegian Offshore Directorate is inviting the companies on the Norwegian continental shelf (NCS) to nominate blocks for the 26th licensing round on the NCS.
Interest in exploration on the Norwegian continental shelf remains high
9/4/2025 The authorities have received applications from 20 companies in the Awards in Predefined Areas (APA) 2025. The deadline for applications was 2 September.
Regulations relating to seabed minerals now stipulated
9/3/2025 With effect from 1 September 2025, the Norwegian Offshore Directorate has now stipulated the Regulations relating to data collection and documentation in mineral activities on the Norwegian Continental Shelf.
New dashboard provides insight into exploration activity on the NCS
9/1/2025 Exploration activity is crucial for future oil and gas production on the Norwegian Continental Shelf (NCS).
Drilling permit for wellbore 6407/1-B-2 H
9/1/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 6407/1-B-2 H in production licence 1121.
Dry well in the Barents Sea (7117/4-1)
9/1/2025 Equinor and its partners have drilled a dry well in the "Deimos" prospect.
Oil and gas condensate discovery in the Norwegian Sea (6506/12-PB-3 H)
8/29/2025 Equinor Energy AS, operator of production licence 094, has proven petroleum in wildcat well 6506/12-PB-3 H.
The Norwegian shelf – a safe harbour in stormy seas
8/27/2025 The Norwegian continental shelf (NCS) is positioned to remain a competitive producer and exporter of oil and gas for many years to come.