Improved recovery from Statfjord Øst

statfjord-oest.png

Statfjord Øst. Illustration: Equinor.

21/08/2023 The licensees in Statfjord Øst have received consent to use new facilities linked to the gas lift project on the field. Expected start-up will be soon.

The project mainly consists of a new gas lift pipeline from Statfjord C and out to the existing subsea templates, and re-drilling of wells to new locations, completed with gas lift. Equinor, operator of production licences 037 and 089, estimates that the project will increase recoverable resources by 3.1 million standard cubic metres (Sm3) of oil and 0.8 billion Sm3 of gas.

“The NPD regards the gas lift project on Statfjord Øst as an important project to improve recovery and value creation from the field. The project will contribute to good resource management and an extended lifetime towards 2040”, says Inger Ubbe, Assistant Director for Licence Management (acting).

Total investments for the gas lift project on Statfjord Øst are estimated at 3,7 billion 2023-kroner.

Petoro, Vår Energi, Inpex Idemitsu and Wintershall are partners in the production licences.

Statfjord Øst is located in the Tampen area in the northern part of the North Sea, seven kilometres northeast of Statfjord.

The field development solution includes two subsea templates for production and one for water injection, which are tied back to the Statfjord C facility. Two production wells have also been drilled from Statfjord C. The field came on stream in 1994.

The wellstream from Statfjord Øst is transported via a pipeline to the Statfjord C facility for processing, storage and export.

Since the gas lift project entails a significant change to the field development plan (PDO), it has also been processed and approved by the authorities.

Contact
postboks@sodir.no

Tel: +47 51 87 60 00

Updated: 23/08/2023

Latest news

Dry well in the Norwegian Sea (6507/2-8)
27/03/2025 Aker BP ASA and its partners have completed drilling on the “Kongeørn” prospect in the Norwegian Sea, 240 kilometres west of Sandnessjøen.
Drilling permit for wellbore 25/11-30 S
27/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 25/11-30 S in production licence 169, cf. Section 13 of the Resource Management Regulations.
Dry well in the North Sea (35/6-6)
26/03/2025 OMV and its partners have drilled a dry well on the “Horatio” prospect in the North Sea.
Production figures Febuary 2025
20/03/2025 Preliminary production figures for February 2025 show an average daily production of 1 938 000 barrels of oil, NGL and condensate.
Drilling permit for wellbore 9/6-1
18/03/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 9/6-1 in production licence EXL006, cf. Section 13 of the Resource Management Regulations.
Drilling permit for wellbore 6405/7-4
17/03/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 6405/7-4 in production licence 1005, cf. Section 13 of the Resource Management Regulations.
Drilling permit for the wells 34/6-8 S and 34/6-8 A
11/03/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for the wells 34/6-8 S and 34/6-8 A in production licence 554, cf. Section 13 of the Resource Management Regulations.
Announcement of acreage for CO2 storage on the Norwegian Continental Shelf
05/03/2025 On 5th of March 2025, the Ministry of Energy announced one area for CO2 storage pursuant to the CO2 Storage Regulations. This area comprises defined blocks in the North Sea.
Gas/condensate discovery in the Norwegian Sea (6406/6-7 S)
05/03/2025 Equinor and its partners have proven gas/condensate in the “Mistral Sør” prospect.
Dry well in the North Sea (7/1-4 S)
04/03/2025 Vår Energi and its partners have drilled a dry well on the “Kokopelli” prospect, south of the Sleipner area.